Bellus Apartments – A Gem Among the Stones
To date over 272,941 construction hours have been put in by Kalmar Construction and team to get Bellus Apartments closer to nearing completion. With the removal of the external scaffold the contemporary facade has now being revealed, showcasing the buildings white, ochre and black exterior. The commencement of landscaping will soon commence bringing even more personality to the building.
Glazing on the gymnasium is being installed with the cedar fences as shown above currently being installed around the building. The storage lockers have been installed in the basement with finishing works in progress. Stair balustrading is currently in progress as well the Ground Level patios waterproofing and tiling.
Moving inside Ground Floor apartments have had their apartments inspected by the consultants with them highlighting any “snags”. As shown by the blue dots in the above image. These snags will then be given to the construction team to remedy before handover to purchasers. Level 1 & 2 apartments will begin their inspections with the consultants next week. Level 3 apartments are having their carpet installed while Level 4 apartments are going through their Final Fix for services such as electrical, plumbing and fire services.
Now that the scaffold is removed and we can see the wonderful facade of Bellus, we are extremely pleased on how the building is taking shape. We still remain on schedule and anticipate settlement will occur 4th Quarter 2017.
See more images at bellus.co.nz